Garden & Outdoor

Gravel Calculator

Cubic yards and tons of gravel for a drive, path or bed, with the compaction allowance included so the load is not short once it is rolled.

Enter your values

Results update instantly as you type.

The area
Area shape
The build
What it is for
Sets a sensible depth and tells you whether a sub-base is needed.
Stone
Buying
Units
Measurement system
Prices are yours to set, so any currency works.

Everything is worked out in your browser, so the numbers never leave your device. The shareable link reopens the calculator with exactly these values.

Results

You need
5.75 tons of crushed stone 3/4 in
300 sq ft at 4 in finished depth
Order by weight
How most yards sell it
5.75 tons
Order by volume
115 cu ft loose
4.26 cu yd
Area
Rectangle
300 sq ft
Finished depth
After rolling
4 in
Compaction added
15 cu ft extra
15%
Sub-base also needed
6 in of crusher run
10.42 tons
Estimated cost
5.75 tons x $45
$258.75
Delivery loads
At about 20 tons a tipper
1
iThis needs a sub-base underneathA driveway wants about 6 in of compacted crusher run below the surface stone, which is a further 6.94 cu yd, roughly 10.4 tons. Without it the surface migrates into the soil.
Compaction allowance addedAngular stone loses about 15% of its loose volume when it is rolled, so the order is 15 cu ft more than the finished depth suggests.
iPut a membrane down firstGravel laid straight onto soil sinks into it and weeds come through. A woven geotextile under the stone is the single thing that decides whether it still looks right in three years.

Working

  1. area = 30 x 10 = 300 sq ft
  2. finished volume = 300 x 4 / 12 = 100 cu ft
  3. loose volume = 100 x 1.15 compaction = 115 cu ft
  4. cubic yards = 115 / 27 = 4.26 cu yd
  5. tons = 4.26 cu yd x 2700 lb / 2000 = 5.75 tons

Quick answer

Gravel is area times depth, plus a compaction allowance. Angular stone loses up to a quarter of its loose volume once it is rolled, so ordering the finished volume leaves a drive short. Yards sell by the ton, so the last step is turning cubic yards into weight at roughly 2,700 lb per cubic yard for crushed stone.

tons = area sq ft x (depth in / 12) x compaction / 27 x lb per cu yd / 2000

Worked example

A 30 ft by 10 ft driveway in 3/4 in crushed stone, 4 in deep.

Order by weight5.75 tons — How most yards sell it
Order by volume4.26 cu yd — 115 cu ft loose
Area300 sq ft — Rectangle
Finished depth4 in — After rolling
Compaction added15% — 15 cu ft extra
Sub-base also needed10.42 tons — 6 in of crusher run
Estimated cost$258.75 — 5.75 tons x $45
Delivery loads1 — At about 20 tons a tipper

Working

  1. area = 30 x 10 = 300 sq ft
  2. finished volume = 300 x 4 / 12 = 100 cu ft
  3. loose volume = 100 x 1.15 compaction = 115 cu ft
  4. cubic yards = 115 / 27 = 4.26 cu yd
  5. tons = 4.26 cu yd x 2700 lb / 2000 = 5.75 tons

The sub-base is the line people skip, and it is usually larger than the surface order. Gravel laid straight onto soil works itself down into it under wheel loads until the drive is mud with stones in it.

Gravel depth and quantity by use

Standard depths, and what 100 square feet takes in crushed stone including a compaction allowance.

UseSurface depthSub-basePer 100 sq ftWeight
Decorative bed2 innone0.71 cu yd0.96 tons
Footpath3 innone1.06 cu yd1.44 tons
Patio sub-base4 innone1.42 cu yd1.92 tons
Driveway4 in6 in1.42 cu yd1.92 tons
Shed or hot tub base4 in4 in1.42 cu yd1.92 tons

Sub-base is compacted crusher run below the surface layer. Multiply the last two columns by your own area over a hundred.

At a glance

What it doesTurns area and depth into cubic yards and tons, with compaction and sub-base
Inputs neededArea, depth, stone type, what the surface is for
Main outputTons to order
Formulatons = area x depth / 12 x compaction / 27 x density / 2000
CategoryGarden & Outdoor
CostFree, no sign-up, no download

How to use the Gravel Calculator

  1. Measure the area. For an irregular shape, break it into rectangles and add the results.
  2. Pick what the surface is for, which sets a sensible depth and tells you whether a sub-base is needed.
  3. Choose the stone. Angular crushed stone for anything that takes traffic, rounded stone only for beds.
  4. Leave the compaction allowance on unless you are ordering loose stone that will not be rolled.
  5. Order by the ton, since that is how yards price it, and add the sub-base as a separate load.

Frequently asked questions

How many tons of gravel in a cubic yard?

About 1.35 tons for crushed stone, 1.4 for pea gravel and 1.5 for crusher run. Densities vary with moisture and stone size, so treat any tonnage as an estimate and order slightly over.

How deep should gravel be for a driveway?

Four inches of angular surface stone over about six inches of compacted crusher run. The surface layer alone is what fails: without a sub-base the stone works down into the soil under wheel loads.

Why does gravel need a compaction allowance?

Loose angular stone has voids between the pieces. Rolling closes them, which is the point, but it means the finished depth is up to a quarter less than the loose depth you ordered.

Can I use pea gravel on a driveway?

It will not stay put. Rounded stone has no interlock, so tyres push it into ruts and spread it onto the lawn. Angular crushed stone locks together under load, which is why drives use it.

Do I need a membrane under gravel?

Yes, a woven geotextile. It stops the stone migrating down into the soil and blocks weeds from below. It is the cheapest part of the job and the one that decides how the surface looks in three years.